City of Breckenridge TXDOT U.S. 183 North – Sewer Relocation

CLIENT: City of Breckenridge
LOCATION: Breckenridge, TX

The City of Breckenridge contracted eHT to provide project management, design and construction administration for the replacement of all existing sewer lines within the TXDOT right-of-way in preparation for the planned rehabilitation for US 183 North from the City’s downtown area to north of the City Limits.  The project included approximately 5,000 linear feet of 4-inch thru 15-inch SDR-26 PVC gravity sewer main along with steel encasement, manholes, service laterals and pavement replacement. The City contracted a utility contractor to construct the improvements and was then reimbursed by TxDOT once the work was complete.  eHT coordinated with the TxDOT Brownwood District on behalf of the City from beginning to end.  The project provided approximately $1.4 million of improvements.